SOW HLT-DC-MCN-001 · Ohana Cloud
Executive Progress Reports
Hult Data Cloud & Marketing Cloud Next engagement.
12 Jun 2026 — Wk 8 close (4–10 Jun) + workshop · SOW DELIVERED · F-20/2026 SENT
SOW closed 8 of 8 weeks · MCN pilot architected end-to-end · 5 UI playbooks shipped to Hult team · Prod SFMC Bounce cleanup breakthrough (5 streams deleted incl. 1.4M Bounce wedged since 21 May) · MC connection recreated · Flow Performance + Marketing Analytics UMA packages installed (Marketing Performance skipped · WebsiteEngagement pre-req gap) · 15-slide MCN pilot deck (4.1MB · Hult brand format · IR + BDT + Token Resolution SVGs) · Token render path = MCN Filter+Sort dialog (documented) · Preference Page Consent app setup verified · 11 PRs merged Wk 8+Wk 9 D1 · ✅ £20k SOW fully invoiced (F-14/15/16/20) · all 4 pending payment
Latest
5 Jun 2026 — Wk 7 wrap (28 May–3 Jun) + Wk 8 Day 1 workshop (Day 50 of 56 · 89% through)
MCN E2E build LIVE in DC sandbox (Segment + EmailContent + Flow + CI active) · Workshop MAT + MCN pilot delivered Thu 4 Jun · 3 of 3 Track B seeds production-ready (Campus + Programme + Staff) · 7 post-workshop priorities P1-P7 roadmap committed · HULT-22242 4-layer block argument sent to SF Engineering · 2nd CI deadlock ticket draft ready · £15k sent of 20k SOW · F-20 pending end Wk 8
28 May 2026 — Wk 6 wrap (21–27 May) + Wk 7 Day 1 (Day 42 of 56 · 75% through)
v5 cross-org IR spec merged (4 normalised gold tables 1:1 with DC DMOs) · Decision #5 Track B campus seed end-to-end live in DC sandbox · GH #334 workshop tracker · 12 decisions locked across Wk 6+7 · #281 naming convention adopted cross-team · Phase 1 connector reauth fully closed · campus harmonisation asymmetry surfaced for workshop
21 May 2026 — End of Week 5 · Halfway point (Day 35 of 56)
10/10 specs locked · 99.66% sandbox deployable · 5 blockers carved with named owners · prod Snowflake↔DC connection live · consent restart with Simon+James · GH #294 SF Engineering escalation opened
14 May 2026 — End of Week 4 + Week 5 Day 1
Architecture decision closed · canonical specs done · 9,099 components deploy-ready (99-100%) · 5 issues closed this week
6 May 2026 — End of Week 3
Pilot scope locked · operating model signed-off · consent architecture decided · 5 issues closed
30 April 2026 — End of Week 2 · SOW checkpoint
Architecture decided · Phase 1 closed · operating-model deck delivered
23 April 2026 — End of Week 1
Discovery + audit kick-off · 7 issues closed